Connect the Landis+Gyr E450 energy meter to the Reduxi Controller via M-Bus and the Reduxi Landis Converter.
1 Technical documentation
Documents for this installation:
- How to configure Landis+Gyr E350 or E450 in the MAP120 tool – Reduxi guide for the M-Bus settings on the meter
- Reduxi Converter for Landis+Gyr E350, 450 meter – Connection and technical data of the Reduxi converter
- Landis+Gyr E450 brochure – Manufacturer data on the meter and its interfaces
2 Required equipment
You need the following components:
- Reduxi Controller or Reduxi Gateway
- Landis+Gyr E450 energy meter
- Reduxi Landis Converter RS485-M-BUS
- Cable between the converter and the controller (A, B and GND)
- Laptop or tablet with internet access to configure the device in Reduxi
3 Set up the M-Bus interface on the meter
To configure the energy meter, follow How to configure Landis+Gyr E350 or E450 in the MAP120 tool.
4 Connect the meter to the Reduxi Controller
4.1 Connect M-Bus on the meter
Connect M-Bus on the energy meter directly to the Reduxi Landis Converter RS485-M-BUS. Use pins 28 and 29 on the energy meter, as shown in the picture.
Text description of this image
Diagram of the terminal layout of an energy meter (Landis+Gyr E450) in three dashed boxes. Left box: voltage and current measurement with three current transformer symbols, terminals 1, 3, 4, 6, 7, 9, 10 and 12, a motor symbol M, and phase lines L1, L2, L3 and N below. Middle box: relay and pulse outputs with terminals 23, 24, 25, 26 (two switch symbols, Uc 230V, Ic 0.1A and Ic 8A; a yellow dot marks terminal 24) and terminals 30 and 31 with a 12V source, LED symbol and I1 pulse symbol (+ on 30, - on 31). Right box: M-BUS block with four terminals in the order 28, 29, 28, 29; the M-BUS box is connected to the terminals with lines and junction dots (28 and 29 on the left connected to the M-BUS box, the other 28 and 29 linked by a second line).
4.2 Connect the converter to the controller
Connect the RS485 side of the Reduxi Landis Converter to the Reduxi Controller or Reduxi Gateway. Choose port one or port two:
- A → A
- B → B
- GND → GND
4.3 Check the converter LEDs
A green light and a blinking yellow light appear on the converter. If the yellow light is not blinking, the energy meter is not set from the electro-distribution and does not send data.
5 Log in to the Reduxi web interface
You can open the Reduxi web interface in two ways:
Text description of this image
Screenshot of three Reduxi mobile app screens side by side, with cyan boxes and number badges 2 to 4. Left screen (dashboard, dark theme): menu icon at top left marked with a box and badge 2; 'reduxi' logo; tabs 'Real time data' (active) and 'Statistics'; price 5.79 € and temperature 3.2 °C; energy flow diagram with a house in the centre (-1.25 kW) and icons with values 69.0 W, 1.3 kW, 1.1 kW (red ring), -165.0 W with 97 % (red ring) and 0.0 W values at the bottom; tabs 'Power' and 'Energy'; bottom navigation: Dashboard, Diagnostics, Device control, Settings. Middle screen (side menu): 'reduxi' logo, 'Number of locations: 1233', heading 'Reduxi device management', entries '+ Add Reduxi location' and 'Reduxi devices' (marked with a box and badge 3), then 'My profile' and 'About app'. Right screen (device page): Back; picture of a black Reduxi controller with two Ethernet ports; status 'Connected'; card 'Update available': 'New update is available for your Reduxi device.' with button 'Download and install update'; card 'Connect to configurator': 'Tunnel connection enables remote access to your Reduxi configurator, without need to be connected to the same local network.' with button 'Activate tunnel connection' (marked with a box and badge 4); card 'Unit details' with field 'Unit ID'.
Text description of this image
Screenshot made of two parts side by side. Left part: Reduxi mobile app screen on a dark background. Top: Back button; picture of a black Reduxi controller with two Ethernet ports and a terminal block; status 'Connected' with a Wi-Fi icon. Card 'Update available': 'New update is available for your Reduxi device.' with button 'Download and install update'. Card 'Connect to configurator' with a key icon: 'Tunnel connection enables remote access to your Reduxi configurator, without need to be connected to the same local network.' and button 'Open configurator', marked with a cyan box and number badge 5. Below: card 'Unit details' with a field 'Unit ID' (value not visible). Right part: Reduxi Configurator opened in a browser, marked with a cyan frame and number badge 6. Header: back arrow, 'Tunnel connection', reload icon. Left sidebar with icons (lightning, chip, lightning bolt, bar chart, gear). Page 'Home' with a green link icon. Green notice: 'New patch available. Click here to apply.' with a close X. Time 09:12:56. Energy flow diagram with a house in the centre (1.700 kW) and icons for grid (0.000 kW), solar (1.700 kW), battery (green, 0.000 kW and 0.800 kW), a device at left (0.900 kW), electric vehicle and a charger or device at bottom. Label 'Energy manager' at the bottom.
http://reduxi.local. You can find the controller's IP address in your router's device list or in the Reduxi app under Reduxi devices.admin · Password: admin (factory default)Text description of this image
Screenshot of the Reduxi Configurator login page in a Chrome browser window. The address bar shows 'Not secure' and 'reduxi.local'; the address bar is marked with a cyan box and an enlarged copy of it (cyan box, text 'Not secure reduxi.local') is shown at the left, connected by a cyan line. Page background: light grey line drawing of a house with solar panels (green), a wall box, an inverter, a car and a charger. Top left: 'reduxi configurator' logo. Login box in the centre with title 'Login', a language selector (English flag, 'English'), a username field and a password field, and a dark 'Login' button.
Text description of this image
Screenshot of the Reduxi Configurator web interface after login, light theme. Top left: 'reduxi configurator' logo. Header bar: 'Home' at left, green 'Connected' status at top right. Left sidebar: expanded section 'Devices' with a list of entries, then collapsed sections 'Manager' and 'Configuration' and 'Settings'. Main area: energy flow diagram. House in the centre with ring, value 24.20 kW. Grid icon at top left, 24.20 kW (red dot on its line). Solar icon at top right, value '-'. Left icon (battery or device), 6.700 kW (green dot on its line). Right icons (battery storage and a device), values '-'. EV charger icon at bottom left, 31.00 kW. A further device icon at bottom right. Label 'Energy manager' below the house.
6 Add the meter to Reduxi
Use these steps to add a new meter or to edit an existing one.
6.1 Basic settings
Log in to the Reduxi Configurator via the browser (see Point 5), click + Add device and enter the basic settings of the meter.
Text description of this image
Screenshot of the Reduxi Configurator form Basic settings. Fields: Device type: Energy meter (dropdown); Type: Landis+Gyr E450 (dropdown); Name: Landis+Gyr E450 (text field). Buttons: Back (outlined, left) and Next (dark, right).
6.2 Communication settings
Select the communication channel.
6.3 Device configuration
Choose the device configuration.
6.4 Test communication
Click Test communication at the bottom of the wizard. It reads the Landis+Gyr E450 once and saves nothing. If the test succeeds, click Done: only Done creates the device.
Text description of this image
Screenshot of the bottom button bar of a Reduxi Configurator page. Left: button 'Back'. Right: button 'Test communication' (marked with a cyan box) and dark button 'Done'.
Text description of this image
Screenshot of the Reduxi Configurator page 'Communication channel and device configuration'. Connection *: TCP/IP (dropdown). IP *: 192.168.50.243, with button 'Scan for IP'. Port *: 502, with button 'Test port'. Modbus unit ID *: 1. Buttons at the bottom: Back (left), Test communication and Done (right). The Done button is marked with a cyan box.
Then enter and choose the advanced settings.
7 Check the readings
7.1 Last measurements
After communication is established, check the values under Devices – Landis+Gyr E450 in the Reduxi Configurator.
✓ Summary
Preparation (Points 1–2): Open the documentation. Prepare the controller, the converter, the cable and a laptop or tablet.
Landis+Gyr E450 (Points 3–4): Set up M-Bus on the meter. Connect pins 28 and 29 to the converter and the converter to the controller.
Add to Reduxi (Points 5–6): Log in to the Reduxi Configurator. Add the device and test communication.
Go live (Point 7): Check the last measurements under Devices.
→ Common issues
| Issue | Solution |
|---|---|
| Yellow LED on the converter is not blinking | The meter is not set from the electro-distribution and sends no data. |
| Test communication fails | Check the optional Block cypher and authentication key parameters. They depend on how the distributor configured the meter. |
| Open configurator does not open or stays empty | The tunnel is not active yet. Wait about 30 seconds and check that the controller is online. |
Login with admin is rejected |
The password was changed during installation. Ask the installer. The Reduxi account password does not work here. |
reduxi.local does not load |
Your device is not in the same network as the controller. Use the IP address or the tunnel connection. |
| Communication test fails, device shows offline | Check reachability, IP address / port / unit ID, and that the protocol is enabled on the device. |